TEN BKC
P51800004889
Behind schedule
This project is about 13 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~13 months.
Registered with RERA
9 Aug 2017Original promised completion
6 Jun 2023The deadline the builder committed to at registration.
Revised deadline after extensions
5 Jun 2025Pushed back ~24 months across 1 extension.
Today — still not completed
About 13 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
9 Aug 2017
When the project was registered with RERA.
6 Jun 2023
The deadline committed to at registration.
5 Jun 2025
After all approved extensions.
—
Handover date, when available.
13 mo overdue12.5 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
103
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 6 Jun 2023 | 5 Jun 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
See MIG (Bandra) Realtors & Builders Private Limited's full track record →
Official records
Builder: MIG (Bandra) Realtors & Builders Private Limited (NAME:MIG (Bandra) Realtors & Builders Private Limited)