SHIV SHAKTI CHSL
P51800007424
Behind schedule
This project is about 43 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~43 months.
Registered with RERA
17 Aug 2017Original promised completion
31 Dec 2019The deadline the builder committed to at registration.
Revised deadline after extensions
22 Nov 2022Pushed back ~35 months across 1 extension.
Today — still not completed
About 43 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
17 Aug 2017
When the project was registered with RERA.
31 Dec 2019
The deadline committed to at registration.
22 Nov 2022
After all approved extensions.
—
Handover date, when available.
43 mo overdue43 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2019 | 22 Nov 2022 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 0 delivered, 3 still active. 2 of 3 (67%) ran late.