WHISPERING TOWERS EFG WINGS

P51800007809

Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 67 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 18 Aug 2017Due 30 Nov 2020

Past deadline by ~67 months.

  1. Registered with RERA

    18 Aug 2017
  2. Original promised completion

    30 Nov 2020

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 67 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

18 Aug 2017

When the project was registered with RERA.

30 Nov 2020

The deadline committed to at registration.

30 Nov 2020

After all approved extensions.

Handover date, when available.

67 mo overdue66.7 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

47

Complaints against the builder

0

Often reported per project on MahaRERA

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 5 projects — 0 delivered, 5 still active. 5 of 5 (100%) ran late.

5 projects5 delayed (100%)

See HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD's full track record →

Official records

View this project on the MahaRERA portal

Builder: HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD (NAME:HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD)

Data last refreshed 21 Jun 2026.