Mumbai Suburban, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 20 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 2 Jan 2018Due 31 Oct 2024

Past deadline by ~20 months.

  1. Registered with RERA

    2 Jan 2018
  2. Original promised completion

    30 Jun 2022

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Oct 2024

    Pushed back ~28 months across 1 extension.

  4. Today — still not completed

    About 20 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

2 Jan 2018

When the project was registered with RERA.

30 Jun 2022

The deadline committed to at registration.

31 Oct 2024

After all approved extensions.

Handover date, when available.

20 mo overdue19.7 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Jun 202231 Oct 2024MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See ASIAD HOUSING AND PROPERTY DEVELOPMENT SERVICES PVT LTD's full track record →

Official records

View this project on the MahaRERA portal

Builder: ASIAD HOUSING AND PROPERTY DEVELOPMENT SERVICES PVT LTD (NAME:ASIAD HOUSING AND PROPERTY DEVELOPMENT SERVICES)

Data last refreshed 22 Jun 2026.