SHREE NEHA CHSL
P51800019288
Behind schedule
This project is about 9 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~9 months.
Registered with RERA
21 Jan 2019Original promised completion
30 May 2022The deadline the builder committed to at registration.
Revised deadline after extensions
30 Sept 2025Pushed back ~40 months across 1 extension.
Today — still not completed
About 9 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
21 Jan 2019
When the project was registered with RERA.
30 May 2022
The deadline committed to at registration.
30 Sept 2025
After all approved extensions.
—
Handover date, when available.
9 mo overdue8.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 May 2022 | 30 Sept 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.