The Greens - Radhakunj
P51800029355
Delivered — but late
This project was completed about 8 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
18 May 2021Original promised completion
31 May 2024The deadline the builder committed to at registration.
Revised deadline after extensions
14 Feb 2025Pushed back ~9 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
18 May 2021
When the project was registered with RERA.
31 May 2024
The deadline committed to at registration.
14 Feb 2025
After all approved extensions.
—
Handover date, when available.
8 mo delay8.5 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 May 2024 | 14 Feb 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 4 delivered, 0 still active. 4 of 4 (100%) ran late by an average of 12 months.
Official records
Builder: Ethics Infra Development Pvt Ltd (NAME:ETHICS INFRA DEVELOPMENT)
Data last refreshed 22 Jun 2026.