SAFAL GOLF RESIDENCES
P51800029994
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Within the planned build window.
Registered with RERA
20 Jul 2021Original promised completion
31 Dec 2024The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jun 2027Pushed back ~30 months across 1 extension.
Today — in progress
About 12 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
20 Jul 2021
When the project was registered with RERA.
31 Dec 2024
The deadline committed to at registration.
30 Jun 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2024 | 30 Jun 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 2 projects — 0 delivered, 2 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: MANGALNATH DEVELOPERS PVT LTD (NAME:MANGALNATH DEVELOPERS)
Data last refreshed 22 Jun 2026.