ADISHAKTI CHS ADITYARAJ PRIME

P51800045695

Mumbai Suburban, MaharashtraOthersOverdue

Behind schedule

This project is about 3 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 6 Jun 2022Due 31 Mar 2026

Past deadline by ~3 months.

  1. Registered with RERA

    6 Jun 2022
  2. Original promised completion

    31 Mar 2026

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 3 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

6 Jun 2022

When the project was registered with RERA.

31 Mar 2026

The deadline committed to at registration.

31 Mar 2026

After all approved extensions.

Handover date, when available.

3 mo overdue2.8 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 2 projects — 0 delivered, 2 still active. 2 of 2 (100%) ran late. Limited history — read the project list before drawing conclusions.

2 projects2 delayed (100%)

See ADITYARAJ BUILDERS & PROMOTERS's full track record →

Official records

View this project on the MahaRERA portal

Builder: ADITYARAJ BUILDERS & PROMOTERS (NAME:ADITYARAJ BUILDERS PROMOTERS)