Navrang Crystal
P51800048561
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
6 Jan 2023Original promised completion
30 Nov 2025The deadline the builder committed to at registration.
Revised deadline after extensions
30 May 2026Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
6 Jan 2023
When the project was registered with RERA.
30 Nov 2025
The deadline committed to at registration.
30 May 2026
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Nov 2025 | 30 May 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 6 months. Limited history — read the project list before drawing conclusions.
Official records
Builder: OXFORD PLANET REALTY LLP (NAME:OXFORD PLANET REALTY)
Data last refreshed 22 Jun 2026.