SPARKLES MITALI BUSINESS CENTRE
P51800055085
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Within the planned build window.
Registered with RERA
29 Feb 2024Original promised completion
5 Apr 2028The deadline the builder committed to at registration.
Today — in progress
About 21 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
29 Feb 2024
When the project was registered with RERA.
5 Apr 2028
The deadline committed to at registration.
5 Apr 2028
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 1 delivered, 2 still active. 1 of 3 (33%) ran late by an average of 16 months.
Official records
Builder: SPARKLE EARTH DEVELOPER (NAME:SPARKLE EARTH DEVELOPER)
Data last refreshed 22 Jun 2026.