Mumbai Suburban, MaharashtraResidential / Group HousingIn progress

Under construction

Currently within its planned build window. Watch the deadline and any new extensions.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 31 Jul 2024Due 15 Jan 2028

Within the planned build window.

  1. Registered with RERA

    31 Jul 2024
  2. Original promised completion

    15 Jan 2028

    The deadline the builder committed to at registration.

  3. Today — in progress

    About 19 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

31 Jul 2024

When the project was registered with RERA.

15 Jan 2028

The deadline committed to at registration.

15 Jan 2028

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 12 projects — 9 delivered, 3 still active. No delays recorded so far.

12 projects0 delayed (0%)100% on time

See ALLIANCE CITY DEVELOPERS REALTORS PVT LTD's full track record →

Official records

View this project on the MahaRERA portal

Builder: ALLIANCE CITY DEVELOPERS REALTORS PVT LTD (NAME:ALLIANCE CITY DEVELOPERS REALTORS)

Data last refreshed 22 Jun 2026.