SOM NIWAS
P51900019850
Behind schedule
This project is about 28 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~28 months.
Registered with RERA
5 Mar 2019Original promised completion
23 Feb 2024The deadline the builder committed to at registration.
Today — still not completed
About 28 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
5 Mar 2019
When the project was registered with RERA.
23 Feb 2024
The deadline committed to at registration.
23 Feb 2024
After all approved extensions.
—
Handover date, when available.
28 mo overdue28 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 23 Feb 2024 | 30 Sept 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: Naman Developers (NAME:Naman Developers)