Siddha Sky Phase 4
P51900021031
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
27 May 2019Original promised completion
30 May 2027The deadline the builder committed to at registration.
Today — in progress
About 11 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
27 May 2019
When the project was registered with RERA.
30 May 2027
The deadline committed to at registration.
30 May 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
2
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 May 2027 | 31 Dec 2030 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 2 projects — 0 delivered, 2 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: Sejal Shakti Realtors LLP (NAME:Sejal Shakti Realtors LLP)
Data last refreshed 21 Jun 2026.