Sumer Samaq Prime
P51900022219
Behind schedule
This project is about 41 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~41 months.
Registered with RERA
5 Sept 2019Original promised completion
31 Jan 2023The deadline the builder committed to at registration.
Today — still not completed
About 41 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
5 Sept 2019
When the project was registered with RERA.
31 Jan 2023
The deadline committed to at registration.
31 Jan 2023
After all approved extensions.
—
Handover date, when available.
41 mo overdue40.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Jan 2023 | 30 Jun 2026 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: Samaq Builders Private Limited (NAME:Samaq Builders Private Limited)
Data last refreshed 21 Jun 2026.