Indiabulls Park 4

P52000000475

Raigarh, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 17 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 18 Jul 2017Due 30 Jan 2025

Past deadline by ~17 months.

  1. Registered with RERA

    18 Jul 2017
  2. Original promised completion

    30 Jan 2025

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 17 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

18 Jul 2017

When the project was registered with RERA.

30 Jan 2025

The deadline committed to at registration.

30 Jan 2025

After all approved extensions.

Handover date, when available.

17 mo overdue16.7 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

30

Complaints against the builder

0

Often reported per project on MahaRERA

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Jan 202530 Dec 2028MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 8 projects — 4 delivered, 4 still active. 4 of 8 (50%) ran late.

8 projects4 delayed (50%)100% on time

See Lucina Land Development Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: Lucina Land Development Limited (NAME:Lucina Land Development Limited)

Data last refreshed 21 Jun 2026.