STUDIO HIGH 5 Phase 2

P52000003207

Raigarh, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 22 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 5 Aug 2017Due 31 Mar 2021

Completed.

  1. Registered with RERA

    5 Aug 2017
  2. Original promised completion

    31 May 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Mar 2021

    Pushed back ~22 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

5 Aug 2017

When the project was registered with RERA.

31 May 2019

The deadline committed to at registration.

31 Mar 2021

After all approved extensions.

Handover date, when available.

22 mo delay22 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 May 201931 Mar 2021MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 22 months. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)0% on time

See RAMSHIROMANI LURKHUR YADAV's full track record →

Official records

View this project on the MahaRERA portal

Builder: RAMSHIROMANI LURKHUR YADAV (NAME:RAMSHIROMANI LURKHUR YADAV)

Data last refreshed 21 Jun 2026.