← Back to search

Marvel Cascada D building

P52100003507

Pune, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 80 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 5 Aug 2017Due 31 Oct 2019

Past deadline by ~80 months.

  1. Registered with RERA

    5 Aug 2017
  2. Original promised completion

    31 Oct 2018

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Oct 2019

    Pushed back ~12 months across 1 extension.

  4. Today — still not completed

    About 80 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

5 Aug 2017

When the project was registered with RERA.

31 Oct 2018

The deadline committed to at registration.

31 Oct 2019

After all approved extensions.

Handover date, when available.

80 mo overdue79.8 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Oct 201831 Oct 2019MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 12 projects — 4 delivered, 8 still active. 7 of 12 (58%) ran late.

12 projects7 delayed (58%)100% on time

See MARVEL SIGMA HOMES PRIVATE LIMITED's full track record →

Official records

View this project on the MahaRERA portal

Builder: MARVEL SIGMA HOMES PRIVATE LIMITED (NAME:MARVEL SIGMA HOMES)

Data last refreshed 24 Jun 2026.