SS STRADA

RERA-GRG-1266-2023

Gurgaon, HaryanaOverdue

Behind schedule

This project is about 3 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 15 May 2023Due 31 Mar 2026

Past deadline by ~3 months.

  1. Registered with RERA

    15 May 2023
  2. Original promised completion

    31 Mar 2026

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 3 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

15 May 2023

When the project was registered with RERA.

31 Mar 2026

The deadline committed to at registration.

31 Mar 2026

After all approved extensions.

Handover date, when available.

3 mo overdue2.8 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On Haryana RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 12 projects — 0 delivered, 12 still active. 9 of 12 (75%) ran late.

12 projects9 delayed (75%)

See SS GROUP PVT. LTD.'s full track record →

Official records

View this project on the Haryana RERA portal

Builder: SS GROUP PVT. LTD. (NAME:SS GROUP)