SMARTWORLD ORCHARD STREET
RERA-GRG-1488-2023
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
18 Dec 2023Original promised completion
30 Jun 2026The deadline the builder committed to at registration.
Today — in progress
Deadline is near.
Timeline & delay
Key dates and how they compare to what was promised.
18 Dec 2023
When the project was registered with RERA.
30 Jun 2026
The deadline committed to at registration.
30 Jun 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 5 projects — 0 delivered, 5 still active. 3 of 5 (60%) ran late.
Official records
Builder: SUPOSHAA REALCON PRIVATE LIMITED (NAME:SUPOSHAA REALCON)
Data last refreshed 23 Jun 2026.