ULTIMUS
RERA-GRG-340-2019
Behind schedule
This project is about 12 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~12 months.
Registered with RERA
23 Dec 2019Original promised completion
29 Jun 2025The deadline the builder committed to at registration.
Today — still not completed
About 12 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
23 Dec 2019
When the project was registered with RERA.
29 Jun 2025
The deadline committed to at registration.
29 Jun 2025
After all approved extensions.
—
Handover date, when available.
12 mo overdue11.8 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
See B D INFRADEVELOPERS PRIVATE LIMITED's full track record →
Official records
Builder: B D INFRADEVELOPERS PRIVATE LIMITED (NAME:B D INFRADEVELOPERS)
Data last refreshed 23 Jun 2026.