INSPIRE
RERA-GRG-520-2019
Behind schedule
This project is about 10 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~10 months.
Registered with RERA
23 Oct 2017Original promised completion
20 Aug 2025The deadline the builder committed to at registration.
Today — still not completed
About 10 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
23 Oct 2017
When the project was registered with RERA.
20 Aug 2025
The deadline committed to at registration.
20 Aug 2025
After all approved extensions.
—
Handover date, when available.
10 mo overdue10.1 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 5 projects — 0 delivered, 5 still active. 1 of 5 (20%) ran late.
Official records
Builder: BRAHMA CITY PVT. LTD. (NAME:BRAHMA CITY)
Data last refreshed 23 Jun 2026.