COBAN RESIDENCES
RERA-GRG-575-2020
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Within the planned build window.
Registered with RERA
16 Oct 2020Original promised completion
10 Mar 2029The deadline the builder committed to at registration.
Today — in progress
About 33 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
16 Oct 2020
When the project was registered with RERA.
10 Mar 2029
The deadline committed to at registration.
10 Mar 2029
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 3 projects — 0 delivered, 3 still active. 1 of 3 (33%) ran late.
Official records
Builder: PAREENA INFRASTRUCTURES PVT. LTD. (NAME:PAREENA INFRASTRUCTURES)
Data last refreshed 23 Jun 2026.