EMERALD HILLS

RERA-GRG-643-2020

Gurgaon, HaryanaOverdue

Behind schedule

This project is about 46 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 29 Aug 2017Due 28 Aug 2022

Past deadline by ~46 months.

  1. Registered with RERA

    29 Aug 2017
  2. Original promised completion

    28 Aug 2022

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 46 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

29 Aug 2017

When the project was registered with RERA.

28 Aug 2022

The deadline committed to at registration.

28 Aug 2022

After all approved extensions.

Handover date, when available.

46 mo overdue45.9 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On Haryana RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 22 projects — 0 delivered, 22 still active. 20 of 22 (91%) ran late.

22 projects20 delayed (91%)

See EMAAR MGF LAND LTD's full track record →

Official records

View this project on the Haryana RERA portal

Builder: EMAAR MGF LAND LTD (NAME:EMAAR MGF LAND)