102 EDEN ESTATE II
RERA-GRG-874-2021
Behind schedule
This project is about 15 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~15 months.
Registered with RERA
21 Sept 2021Original promised completion
31 Mar 2025The deadline the builder committed to at registration.
Today — still not completed
About 15 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
21 Sept 2021
When the project was registered with RERA.
31 Mar 2025
The deadline committed to at registration.
31 Mar 2025
After all approved extensions.
—
Handover date, when available.
15 mo overdue14.8 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 16 projects — 0 delivered, 16 still active. 9 of 16 (56%) ran late.
See COUNTRYWIDE PROMOTERS PRIVATE LIMITED's full track record →
Official records
Builder: COUNTRYWIDE PROMOTERS PRIVATE LIMITED (NAME:COUNTRYWIDE PROMOTERS)
Data last refreshed 23 Jun 2026.