GROUP HOUSING CGEWHO PHASE I

RERA project status · delays · complaints · CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGAN

UPRERAPRJ1005

Uttar PradeshCompleted

Delivered — but late

This project was completed about 15 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 1 Aug 2017Due 27 May 2022

Completed.

  1. Registered with RERA

    1 Aug 2017
  2. Original promised completion

    28 Feb 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    27 May 2022

    Pushed back ~15 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

1 Aug 2017

When the project was registered with RERA.

28 Feb 2021

The deadline committed to at registration.

27 May 2022

After all approved extensions.

—

Handover date, when available.

15 mo delay15 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
28 Feb 202127 Aug 202127-08-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)
27 Aug 202127 May 2022—

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 15 months. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)0% on time

See CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGAN's full track record →

Official records

View this project on the UP RERA portal

Builder: CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGAN (NAME:CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGAN)