Golden Grande (Phase-2)
RERA project status · delays · complaints
UPRERAPRJ434216
Behind schedule
This project is past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~1 month.
Registered with RERA
2 Nov 2023Original promised completion
30 Sept 2026The deadline the builder committed to at registration.
Today — still not completed
About 1 month past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
2 Nov 2023
When the project was registered with RERA.
30 Sept 2026
The deadline committed to at registration.
30 Sept 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Official records
Data last refreshed 20 Jun 2026.