Trident Embassy Phase-3 (Towers J,K,L & Comm)

UPRERAPRJ6492

Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is about 53 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 31 Jul 2017Due 9 Jan 2022

Past deadline by ~53 months.

  1. Registered with RERA

    31 Jul 2017
  2. Original promised completion

    31 Dec 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    9 Jan 2022

    After 1 extension.

  4. Today — still not completed

    About 53 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

31 Jul 2017

When the project was registered with RERA.

31 Dec 2021

The deadline committed to at registration.

9 Jan 2022

After all approved extensions.

Handover date, when available.

53 mo overdue53.4 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 20219 Jan 2022

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 3 projects — 0 delivered, 3 still active. 3 of 3 (100%) ran late.

3 projects3 delayed (100%)

See TRIDENT INFRA HOMES PVT. LTD.'s full track record →

Official records

View this project on the UP RERA portal

Builder: TRIDENT INFRA HOMES PVT. LTD. (UPRERAPRM1568)

Data last refreshed 20 Jun 2026.