F PREMIERE (PHASE 2)
UPRERAPRJ7173
Behind schedule
This project is about 4 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~4 months.
Registered with RERA
1 Aug 2017Original promised completion
30 Oct 2021The deadline the builder committed to at registration.
Revised deadline after extensions
28 Feb 2026Pushed back ~52 months across 4 extensions.
Today — still not completed
About 4 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
1 Aug 2017
When the project was registered with RERA.
30 Oct 2021
The deadline committed to at registration.
28 Feb 2026
After all approved extensions.
—
Handover date, when available.
4 mo overdue3.8 mo
How far past deadline an ongoing project is.
4
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Oct 2021 | 29 Apr 2022 | 29-04-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 29 Apr 2022 | 28 Jan 2024 | — |
| 28 Jan 2024 | 30 Jun 2025 | — |
| 30 Jun 2025 | 28 Feb 2026 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 0 delivered, 3 still active. 3 of 3 (100%) ran late.
See HOME AND SOUL INFRATECH PRIVATE LIMITED's full track record →
Official records
Builder: HOME AND SOUL INFRATECH PRIVATE LIMITED (UPRERAPRM2392)
Data last refreshed 20 Jun 2026.