Golden I Phase-III
RERA project status · delays · complaints
UPRERAPRJ732580
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
5 Jan 2022Revised deadline after extensions
24 Aug 2026After 1 extension.
Today — in progress
About 1 month left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
5 Jan 2022
When the project was registered with RERA.
—
The deadline committed to at registration.
24 Aug 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| — | 24 Aug 2026 | — |
Official records
Data last refreshed 20 Jun 2026.