BHS-17 LOHIYA ENCLAVE OMICRON-1A
UPRERAPRJ9632
Behind schedule
This project is about 76 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~76 months.
Registered with RERA
14 Aug 2017Original promised completion
23 Jun 2019The deadline the builder committed to at registration.
Revised deadline after extensions
20 Feb 2020Pushed back ~8 months across 2 extensions.
Today — still not completed
About 76 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
14 Aug 2017
When the project was registered with RERA.
23 Jun 2019
The deadline committed to at registration.
20 Feb 2020
After all approved extensions.
—
Handover date, when available.
76 mo overdue76 mo
How far past deadline an ongoing project is.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 23 Jun 2019 | 31 Dec 2019 | — |
| 31 Dec 2019 | 20 Feb 2020 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 5 projects — 0 delivered, 5 still active. 5 of 5 (100%) ran late.
See GREATER NOIDA INDUSTRIAL DEVELOPMENT AUTHORITY's full track record →
Official records
Builder: GREATER NOIDA INDUSTRIAL DEVELOPMENT AUTHORITY (UPRERAPRM14590)
Data last refreshed 20 Jun 2026.