← Back to search

RPS-06/2022

UPRERAPRJ985835

Gautam Buddha Nagar, Uttar PradeshNewIn progress

Under construction

Currently within its planned build window. Watch the deadline and any new extensions.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 2 Sept 2022Due 31 Dec 2027

Within the planned build window.

  1. Registered with RERA

    2 Sept 2022
  2. Original promised completion

    31 Dec 2027

    The deadline the builder committed to at registration.

  3. Today — in progress

    About 18 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

2 Sept 2022

When the project was registered with RERA.

31 Dec 2027

The deadline committed to at registration.

31 Dec 2027

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 13 projects — 4 delivered, 9 still active. 9 of 13 (69%) ran late by an average of 13 months.

13 projects9 delayed (69%)25% on time

See YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY's full track record →

Official records

View this project on the UP RERA portal

Builder: YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY (NAME:YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY)

Data last refreshed 20 Jun 2026.