GANGA GLOBAL HOMES PRIVATE LIMITED
NAME:GANGA GLOBAL HOMES
B73/100
Good track record
Tracking 3 projects — 0 delivered, 3 still active. 1 of 3 (33%) ran late.
Delivery breakdown
How this builder's 3 tracked projects are split by outcome.
Key numbers
Total projects
3
Active
3
Completed
0
Delayed
1 (33%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
0%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (3)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
RERA-GRG-1779-2024 Gurgaon · HR | Gurgaon HR | 14 Jan 2025 | 6 Mar 2026 | Overdue | 4 mo overdue |
RERA-GRG-2037-2025 Gurgaon · HR | Gurgaon HR | 9 Oct 2025 | 17 Feb 2028 | In progress | On track |
RERA-GRG-1452-2023 Gurgaon · HR | Gurgaon HR | 23 Oct 2023 | 23 Feb 2028 | In progress | On track |