GANGA VALLEY

RERA-GRG-1779-2024

Gurgaon, HaryanaOverdue

Behind schedule

This project is about 4 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 14 Jan 2025Due 6 Mar 2026

Past deadline by ~4 months.

  1. Registered with RERA

    14 Jan 2025
  2. Original promised completion

    6 Mar 2026

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 4 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

14 Jan 2025

When the project was registered with RERA.

6 Mar 2026

The deadline committed to at registration.

6 Mar 2026

After all approved extensions.

Handover date, when available.

4 mo overdue3.6 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On Haryana RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Good track record

Tracking 3 projects — 0 delivered, 3 still active. 1 of 3 (33%) ran late.

3 projects1 delayed (33%)

See GANGA GLOBAL HOMES PRIVATE LIMITED's full track record →

Official records

View this project on the Haryana RERA portal

Builder: GANGA GLOBAL HOMES PRIVATE LIMITED (NAME:GANGA GLOBAL HOMES)

Data last refreshed 23 Jun 2026.