MILAN INTERBUILT PRIVATE LIMITED

RERA delivery track record · complaints · project delays

NAME:MILAN INTERBUILT

Poor track record

Tracking 5 projects — 3 delivered, 2 still active. 3 of 5 (60%) ran late by an average of 6 months.

Delivery breakdown

How this builder's 5 tracked projects are split by outcome.

1 Delivered on time2 Delivered late2 Overdue

Key numbers

Total projects

5

Active

2

Completed

3

Delayed

3 (60%)

Late or overdue

Avg delay

6 mo

Worst: 12 mo

On-time rate

33%

Of completed projects

Extension rate

80%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (5)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51800003357
Mumbai Suburban · MH
Mumbai Suburban
MH
5 Aug 201731 Mar 2018CompletedOn track
P51800008647
Mumbai Suburban · MH
Mumbai Suburban
MH
19 Aug 201731 Mar 2018Completed12 mo delay
P51800018586
Mumbai Suburban · MH
Mumbai Suburban
MH
21 Nov 201830 Jun 2021Overdue39 mo overdue
P51800032172
Mumbai Suburban · MH
Mumbai Suburban
MH
14 Dec 202131 Dec 2024OverdueOn track
P51800046482
Mumbai Suburban · MH
Mumbai Suburban
MH
5 Aug 202228 Feb 2025Completed6 mo delay