Milan Bliss
P51800046482
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
5 Aug 2022Original promised completion
28 Feb 2025The deadline the builder committed to at registration.
Revised deadline after extensions
31 Aug 2025Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
5 Aug 2022
When the project was registered with RERA.
28 Feb 2025
The deadline committed to at registration.
31 Aug 2025
After all approved extensions.
—
Handover date, when available.
6 mo delay6.1 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 28 Feb 2025 | 31 Aug 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 2 delivered, 2 still active. 3 of 4 (75%) ran late by an average of 9 months.
Official records
Builder: Milan Interbuilt Private Limited (NAME:MILAN INTERBUILT)